Stafford County has opened approximately 1,200 linear feet of new sidewalk along Staffordboro Boulevard between the Juggins Road Connector and Pike Place. The five-foot-wide concrete path connects several residential communities to existing sidewalks, nearby businesses and the Park and Ride lot. It also adds crosswalks, ADA-accessible ramps and detectable warning surfaces.
Those are legitimate public benefits. Pedestrian connections and safer crossings matter, particularly in a county where many neighborhoods were built without a complete sidewalk network. But the project’s reported cost deserves much closer examination.
Stafford County lists the total project cost at $2,147,296—equal to approximately $1,789 for every linear foot of sidewalk.
What the $2.1 million includes
That produces a whole-project cost of approximately $1,789 per linear foot, $358 per square foot of five-foot-wide sidewalk and $9.45 million per mile if the same rate were extended for a full mile.
These numbers are not the unit price paid for concrete. They include design, land acquisition, road crossings, accessibility improvements and other public-project expenses. Even after making that distinction, the total is striking.
The estimate nearly doubled
Stafford’s earlier Capital Improvement Program estimated the project at $1,077,500, or roughly $898 per linear foot. By the 2022 public-hearing stage, available funding had increased to $1,785,000. The County now lists $2,147,296.
The current figure is approximately $1.07 million higher than the original estimate—a 99% increase. The construction allocation alone rose from $885,000 in the 2022 hearing materials to $1,332,913, an increase of about $447,913, or 51%.

How does it compare with other pedestrian projects?
VDOT says paved side paths can range from approximately $250,000 to $5 million per mile, depending on terrain, structures, environmental mitigation, crossings, right-of-way and other design conditions. Staffordboro’s whole-project figure equates to about $9.45 million per mile. Its construction phase alone equates to approximately $5.86 million per mile.
This is not a perfect apples-to-apples comparison. A side path is not identical to this sidewalk, and Staffordboro includes several crossings and accessibility work. The comparison nevertheless shows why a detailed public accounting is reasonable.
How can it be “under budget” if the estimate nearly doubled?
At the ribbon cutting, Board of Supervisors Chairman Deuntay Diggs said the County completed the project “on time and under budget.” That statement may be accurate when the final spending is compared with the latest authorized budget. It does not explain why the published figure increased from about $1.08 million to $2.15 million.
The final construction contract amount, contractor payments, contingency remaining at closeout, change orders, the causes of cost growth, and the exact contribution from each federal and local funding source.
Until those closeout records are available, the $2,147,296 figure should be described as the County’s currently published project cost or funding figure—not necessarily the final amount actually spent.
Federal funding is still public money
The County identifies federal Transportation Alternatives, Congestion Mitigation and Air Quality, and Carbon Reduction funding, along with local revenue. Federal assistance reduces Stafford’s direct local share, but it does not make the project free. Every source is public money, and local funds committed here cannot be used for another transportation need.
The timing matters to taxpayers
The sidewalk opened after Stafford adopted a higher real-estate tax rate for fiscal year 2027. The base rate increased from $0.9236 to $0.9675 per $100 of assessed value, and the Fire and Emergency Services levy also increased. When residents are being asked to pay more, government has a greater obligation to show that capital projects were competitively priced, carefully managed and fully documented.

The central question is value
The issue is not whether Stafford should build sidewalks. Safe pedestrian infrastructure is a legitimate public responsibility. The question is whether this relatively short connection was delivered at a reasonable cost—and whether residents have been given enough information to judge.
A ribbon cutting marks completion. It should not end the financial review. Stafford County should publish the original and final contracts, complete change-order log, final contractor payment, actual engineering and right-of-way expenditures, remaining contingency and a clear explanation of the increase from $1.08 million to $2.15 million.
Save Stafford’s position: Residents can appreciate a safer sidewalk while still questioning its price. When tax bills are increasing, taxpayers deserve more than a ribbon and an assurance that a project was “under budget.” They deserve the final numbers.
Sources, documents & image credits